Back to ArticlesBack

Subscribe to our newsletter

Get the latest articles and resources sent straight to your inbox.

MPUG

Want to continue creating great Microsoft Project Schedules? Last time I shared three best practice “DO’s” to follow on scheduling. This time I’ll share three things to avoid.

DON’T Use the Start and Finish Columns

Microsoft Project is a scheduling tool with a true passion for dynamic information. In other words, it works best when you link tasks together and don’t force actual dates.

In an earlier article, I wrote about flaws in the use of Project. The use of the start and finish columns is a major flaw. And I see this happening with both first-time and veteran users of the product.

The way to see if a project schedule uses the start and finish columns excessively is by the blue (or red) calendar icon in the indicator column:

Erik_van_Hurck_Donts_of_Scheduling_figure_1

If almost all tasks have these calendars, you’re surely using the columns that set a constraint on either the start or finish dates.

How do you fix this? Add the “type” and the “constraint date” columns to any Gantt view you have and either delete the constraint date value or change the type to “as soon as possible” or “as late as possible.”

Erik_van_Hurck_Donts_of_Scheduling_figure_2

DON’T Mistake Work for Duration

A common mistake derived from miscommunication is taking duration for work or vice versa. Consider this short conversation between a project manager and a team member:

PM: “How much time will you need to finish the design?”

TM: “I guess I’ll need three weeks.”

Now will the PM consider the reply as three weeks of duration? Or will the team member need 120 hours of work for the design?

The conversation shouldn’t end with this single question, but rather contain at least two follow-up questions:

PM: “Three weeks of work or will you be done after three weeks?”

TM: “Oh, the work will take me maybe 24 hours.”

PM: “So why will it take you three weeks to finish it? Can I help to speed that up?”

TM: “I have some other unfinished business, but if Dave can help me out, I’ll have the design finished by next week.”

Asking the right questions to get a complete view is essential to get a solid and correct schedule.

DON’T Use Manually Scheduled Tasks in Combination with Work

It’s time to get a bit more technical now. Microsoft introduced “manually-scheduled” tasks in the 2010 version of Project.

Erik_van_Hurck_Donts_of_Scheduling_figure_3

This new feature gave project managers the option to generate early sketch versions of any schedule. But it’s not intended for use in a schedule that’s on its way.

Dan Renier did an excellent video presentation where he describes everything you need to know about the manually-scheduled functionality. A key feature of his presentation at the Project 2014 Conference in Anaheim is that the manually scheduled task won’t be suitable for any task that has an assignment.

As he explains in the presentation, the automatically scheduled tasks will keep the task type you assigned to it intact whereas the manually-scheduled task will throw it out the window and keep a “fixed duration” task type even where this hasn’t been applied.

A Bonus! DON’T Forget Murphy

Change will happen in your schedule! Be prepared and keep these three aspects of a project manager at the top of your toolbox:

  • Communicate;
  • Document; and
  • Evaluate

Communicate

Keep an open door policy with your team members and other stakeholders, but don’t wait for them to come to you with issues or requests. Get a formal structure of frequent meetings with stakeholders in the project.

Document

Documentation is a tedious job, but someone needs to formalize decisions, and there needs to be a clear and uniform understanding of the current situation the project is in. If you document every scope change, issue and risk in the schedule, you come prepared when Murphy knocks on your door. And you can send that jerk on his way as soon as possible.

Evaluate

Once your project is done, get the team back in a room and openly evaluate how the project went. Thank them for their commitment and tell them if the project was a financial success. But also ask them how the next project would be even better and ask them to evaluate you as their project manager. That will help ensure both your team and you grow.

Image Source 

 _________________________________________________________________________________________________________________

Have a “DON’T” best practice of your own? Share it in the comments below!

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

3 Incorrect Ways to Do Scheduling with Microsoft Project

Want to continue creating great Microsoft Project Schedules? Last time I shared three best practice “DO’s” to follow on scheduling. This time I’ll share three things to avoid. DON’T Use […]

4 min read
•over 9 years ago••
E
Erik van HurckAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Erik van Hurck

Content Writer

Erik van Hurck is a Senior PPM consultant for Projectum, a western European Microsoft Partner with offices in Denmark and The Netherlands. On top of that Erik is a Microsoft MVP. As such, Erik assists enterprise customers to adopt the new Power Platform cloud solutions for Project and Portfolio Management. Beyond writing for MPUG, Erik also has a personal blog (www.theprojectcornerblog.com).

View all articles by Erik van Hurck
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
about 2 months ago
Read
Explore All Articles