Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Many project managers like to manage their projects by focusing on the Critical Path. Remember that the Critical Path consists of all tasks with a Total Slack value of 0 days. All tasks on the Critical Path are known as Critical tasks, and cannot slip without impacting the final Finish date of the entire project. I like to describe Critical tasks as the tasks that have no “wiggle room” or “no room for things to go wrong.” If a Critical task slips, then the Finish date of the entire project slips as well. For example, if a Critical task slips by 5 days, then the Finish date of the entire project is now 5 days late as well.

Managing a project by the Critical Path is a good thing, as it allows you to focus your efforts on the tasks that have the most impact the final Finish date of the project. However, have you ever had a non-Critical task slip, and then your project Finish date slipped as well? If so, then it would be good for you to know how to display the “Nearly” Critical Path in your project.

Before I describe how to see the “Nearly Critical Path”, let me remind you how to see the true Critical Path. In either Microsoft Project 2010 or 2013, complete the following steps to display the Critical Path:

  1. Display the regular Gantt Chart view.
  2. Click the Format tab to display the Format ribbon.
  3. In the Bar Styles section of the Format ribbon, select the Critical Tasks checkbox as shown in Figure 1.

criticalpath1
Figure 1: Select the Critical Tasks checkbox

Microsoft Project indicates the Critical Path by displaying red Gantt bars for Critical tasks and blue Gantt bars for non-Critical tasks, as shown in Figure 2. Notice that the Critical Path begins with task ID #5, the Perform Server Stress Test task. The Critical Path also includes all of the tasks in the TESTING phase of the project and the last few tasks in the TRAINING phase of the project.

criticalpath2
Figure 2: Critical Path displayed with red Gantt bars

A key question to ask at this point is, “Why are the first three tasks non-Critical tasks instead of being Critical tasks?” To answer this question, we need to apply the Schedule table by completing the following steps:

  1. Click the View tab to display the View ribbon.
  2. In the Data section of the View ribbon, click the Table pick list button and select the Schedule table, as shown in Figure 3.

criticalpath3
Figure 3: Apply the Schedule table

  1. Drag the split bar to the right edge of the screen so that you can see the Total Slack column.

The Total Slack column tells you how many days late a task can finish without impacting the Finish date of the entire project. Notice in Figure 4 that the first three tasks have 2 days of Total Slack each. This means these tasks can slip a total of 2 days without impacting the final Finish date of the project. If any of these tasks slips a total of 3 or more days, then the final Finish date of the project will slip as well. In other words, sometimes a non-Critical task slips, and the final Finish date of the project slips as well.

criticalpath4
Figure 4: Schedule table shows tasks with slack

The “Nearly” Critical Path is the series of tasks that have a Total Slack value greater than 0 days, but are “nearly” on the Critical Path. In your own projects, the “nearly” Critical tasks might have 1 or 2 days of Total Slack, or they might even have 10 or more days of Total Slack in a large, long-duration project. In my case, I would like the Critical Path to include “nearly” Critical tasks that have 2 days or less of Total Slack. This way, I will be able to see the true Critical Path, along with the “Nearly” Critical Path as well. To display the “Nearly” Critical Path, complete the following steps:

  1. Click the File tab and then click the Options button in the Backstage. Microsoft Project displays the Project Options dialog.
  2. In the Project Options dialog, click the Advanced tab and then scroll down to the bottom of the dialog.

In the Calculation options for this project section of the dialog, notice the last option at the bottom of the dialog, which is the Tasks are critical if slack is less than or equal to _____ days option shown in Figure 5. This is the option you use to display the “Nearly” Critical Path, along with the true Critical Path. If you want to see “nearly” Critical tasks that have 2 days of Total Slack, change this option to 2 days. If you want to see “nearly” Critical tasks that have 10 days of Total Slack, change this option to 10 days.

criticalpath5
Figure 5: Project Options dialog, Advanced page

  1. In the Calculation options for this project section of the dialog, specify a value greater than 0 days in the Tasks are critical if slack is less than or equal to _____ days option.
  2. Click the OK button.

In my project, I want to include tasks with up to 2 days of Total Slack in the Critical Path, so I changed the Tasks are critical if slack is less than or equal to _____ days option to 2 days. Figure 6 shows the Gantt Chart after changing this option. Notice that the first three tasks now have red Gantt bars instead of the blue Gantt bars they had previously.

criticalpath6
Figure 6: “Nearly” Critical Path displayed in the Gantt Chart

At this point, you are probably saying to yourself, “OK, great. I can now see the true Critical Path (tasks with 0 days of Total Slack) and the ‘Nearly’ Critical Path (tasks with Total Slack of up to 2 days), but how can I tell the difference?” There are several methods you can use to determine which tasks are truly Critical and which tasks are “nearly” Critical.

The first method is to right-click on the Task Name column header, to select the Insert Column item on the shortcut menu, and to select the Total Slack column. Doing this will temporarily insert the Total Slack column to the right of the Task Name column. In the Total Slack column header, click the AutoFilter pick list arrow button and select a value. If you want to see only true Critical tasks, select only the 0 days value. If you want to see the “nearly” Critical tasks, select the value you specified in the Project Options dialog. For example, Figure 7 shows the project when I AutoFilter for tasks with 2 days of Total Slack to see the “nearly” Critical tasks.

criticalpath7
Figure 7: Nearly Critical tasks

The second method is to create a custom filter that displays “nearly” Critical tasks and then apply the new filter as a Highlight filter. To create the filter, click the View tab to display the View ribbon. In the Data section of the View ribbon, click the Filter pick list and select the New Filter item. In the Filter Definition dialog, set up your filter criteria similar to those shown in Figure 8 and then click the Save button.

criticalpath8
Figure 8: Filter Definition dialog

To apply the new custom filter as a Highlight filter, click the Highlight pick list in the Data section of the View ribbon, and then select your new custom filter. For example, Figure 9 shows my project with the new _Nearly Critical Tasks filter applied, highlighting in yellow all tasks that are “nearly” Critical tasks. This helps me to easily distinguish between “nearly” Critical task and true Critical tasks.

criticalpath9
Figure 9: Nearly Critical tasks highlighted in yellow

A version of this article originally appeared on the Sensei Project Solutions blog.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Manage Your Projects Using the “Nearly” Critical Path

Many project managers like to manage their projects by focusing on the Critical Path. Remember that the Critical Path consists of all tasks with a Total Slack value of 0 […]

6 min read
•almost 12 years ago•Updated 6 months ago•
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

What PMs Want From AI vs. What’s Actually Happening
Articles
1 min read

What PMs Want From AI vs. What’s Actually Happening

Most project managers want to master AI but few actually use it, and the current research shows the gap is a clarity problem, not a personal failing.

A
Anonymous
10 days ago
Read
Why the End of Project Online Might Be the Best Thing for Your Team
Articles
1 min read

Why the End of Project Online Might Be the Best Thing for Your Team

Project Online retires September 30, 2026, and Eric and Jeff Christoph make the case that the smartest move is a complete desktop project-controls environment, not a one-for-one swap.

A
Anonymous
20 days ago
Read
The Catch-22 Project: Why Some Projects Fail Before They Ever Begin
Articles
1 min read

The Catch-22 Project: Why Some Projects Fail Before They Ever Begin

Learn to spot a Catch-22 project, where contradictory requirements make progress impossible, and how to reframe the structure so your team can move forward.

A
Anonymous
20 days ago
Read
Explore All Articles